CHP installation at UZ Antwerp

blank

Installation and maintenance of CHP 1.5 MWe

Two 1000-litre buffer tanks make CHP more cost-effective and flexible

Renovation of domestic hot water system

Results

Payback in 3 years

Saving 700,000 Euros in costs per year

 

 

 

In 2015, Antwerp University Hospital was looking for a solution to expand heat production while reducing energy consumption. Luminus Solutions installed a 1.5 MWe CHP plant and optimised the entire sanitary hot water system. The new installation was paid for in less than 3 years and still provides the UZ Antwerpen with savings of approximately 30% on its annual energy bill.

 

 