Energy Efficiency and Sustainable Biogas Generation at the Alken-Maes Brewery Site

blank

What was our approach?

At Alken-Maes, Luminus Solutions replaced the outdated biogas CHP unit with a new, more efficient 250 kWe installation from manufacturer 2G. The new engine was integrated into the existing housing, combined with an upgraded control panel, gas analysis cabinet, and improved temperature regulation. To further enhance the reliability of the biogas supply, an activated carbon filter was added.

Thanks to thorough preparation and the reuse of several existing components — such as the flue gas cooler and gas scrubbing system — we successfully delivered the entire installation within a downtime period of just twelve weeks. This project reinforces the brewery’s energy efficiency and continues the strong, sustainable partnership between Luminus Solutions and Alken-Maes.

What was the result?

New 250 kWe biogas CHP unit ensures continuous local energy generation

Installation integrated into existing infrastructure for minimal disruption

Enhanced control and monitoring through upgraded panels and sensors

Added activated carbon filter increases reliability and system lifespan

Downtime limited to 12 weeks including full commissioning

€400,000 investment ensures 10 years of reliable and sustainable energy

New maintenance contract guarantees performance and service continuity